Galleries
Before Restoration Begins
Preliminary Work
Photographs taken at the Darley Dale yard show the condition of RS8 before restoration
begins, and the scale of the task ahead.
Before RS8 can be dismantled any pipes or fittings connecting the various components
to the chassis must be removed.
RS8 is brought inside to carry out this work
From Wirksworth to Darley Dale
On the 16th June 2010 Andrew and Peter Briddon brought RS8 from The National Stone
Centre at Wirksworth to join the Andrew Briddon Loco Collection at Darley Dale.
Dismantling Begins
RS8 is taken outside once again so that the work of dismantling the loco can
commence.
Some parts will be taken to Matlock for shotblasting.
Other parts will be taken by road to the Sigma6 Workshops at
Tunstead Quarry for refurbishment.
Down to the Chassis
The chassis is brought back into Geoffrey Briddon Building so that the chassis can be
dismantled. The front leaf springs are removed and signs of welding reveal where the
chassis was extended to accommodate the diesel power unit.
The Last Bits
The last components are removed from RS8 chassis before it will be parted from its
axles.
The Gearbox, Torsion Bar, Suspension, Braking system are all removed..
Dismantling Complete!
The final part of the dismantling process is to lift the chassis from the axles.
The Sigma 6 Grove crane is brought down from Tunstead to carry out the work.
Starting to Look Like a Loco Again
May and June saw the axles and gearbox reunited with the chassis and cab
Bit by Bit…
July was a hot month and work continued on RS8. Several smaller components,
including hooks, vacuum tank, etc were fitted to the loco, while larger items like the
engine were made ready for installing.
The Engine is Back in the Chassis
September saw the engine installed into the chassis. Components were added to the
exterior and interior of the cab. Buffers and springs were fitted and the wheel rods were
made ready for the wheels.
Historic Photographs
Photographs of RS8 and other locos at work in Tunstead Quarry, Derbyshire
Rebuilding Begins
Less than five months since the project started, the rebuilding of RS8 begins.
The chassis has been shotblasted and painted in primer. The axles have been stripped,
and a ‘new’ part has arrived at the Geoffrey Briddon building.
Preparing to reassemble
The fabrication work on the chassis is complete and the frame is painted black in the
Sigma6 spray booth.
The engine still requires work to be done before the test run.
Over in the ‘brick shed’ refurbished parts are arriving and awaiting reassembly.
Back where it all began
RS8 will be reassembled in the same place as where she was converted to a diesel
locomotive. In the loco workshop of South Central Workshops.
The axle boxes are fitted to the axles and the gearbox is lifted into position.
The chassis awaits its turn to be lifted and lowered onto the axles
A Lick of Paint
During October the exhaust was fitted. Handrails were restored and refitted to the rear
cab. The handbrake chain was fitted. The engine was painted into high temperature
grey paint.
Bit by Bit…
November / December 2018
The Engine is Back in the Chassis
January 2019
Basking in the Sun
SA beutiful April day finds RS undertaking some rail runs outside Tunstead House in the
spring sunshine
Chevrons and Windows
The front and rear chevrons are being applied and RS8 has a sparkling new set of
windows.
Apprentices Lend a Hand
A team of Tarmac apprentices join the effort to help complete some of the outstanding
tasks
Full Colours
A rail run outside Tunstead House in October sees RS8 fully painted in her original clour
scheme and with RS8 nuber applied.
A Temporary Home
On Saturday 23rd November 2019 RS8 moved from the Tunstead workshops to take up
temporary residence in the Tunstead Sidings maintenance facility.